Yale Science Building: Project Schedule

Construction on the Yale Science Building begins with demolition of J.W. Gibbs Laboratory in Fall 2016, with all project work scheduled for completion in Fall 2019. Updated schedules for construction activities will be posted periodically.

Fall 2016 - Early Winter 2017

Site and Utilities Enabling work, with demolition of JW Gibbs toward the end of Fall. 

Please note that demolition consists of a slow deconstruction of the building interiors and exterior elements; not an immediate removal of the building from the site.

Late Winter - Spring 2017 Excavation of project site.