Existing conditions at Kline Geology Laboratory, courtesy of Turner Construction
September 23, 2021
On September 8, the team responsible for the Peabody Museum renovation and addition and Kline Geology Laboratory code upgrades held a town hall meeting to review the project...
Aerial view of the active program area at Science Hill, photo courtesy of Gilbane Building Company
September 16, 2021
Pedestrian, parking, and building closures will be in effect from Friday, September 18, through Wednesday, September 29, due to construction in the area between Sterling...
Southeast walkway by the Yale Science Building, Science Hill, photo by Rob Desanto
June 14, 2021
Pedestrian and parking closures will be in effect from Friday, June 18, through Monday, June 21, due to a crane raise in the Peabody Museum of Natural History’s courtyard....
Science Hill during construction of Sachem's Wood, 2021, photo by Fly on the Wall Productions
October 6, 2020
With the continuation of construction at Sachem’s Wood, and the start of construction at Kline Tower, the overall Science Hill logistics plan was updated to reflect...
Rendering of the future Peabody Museum, courtesy of Centerbrook Architects and Planners
August 7, 2020
On August 6, the Peabody Museum renovation and addition project team held a town hall meeting to review the project schedule and site logistics plans. To learn more about the...
Kline Geology Laboratory, photo courtesy of the Office of Facilities
August 5, 2020
This fall, construction will begin on an interior renovation project to upgrade the life-safety systems and renovate select areas within Kline Geology Laboratory (KGL). On...
Kline Tower in fall, photo by Michael Marsland
February 27, 2020
On February 19, the Kline Tower project team discussed the overall project schedule and impacts as well as pedestrian access routes for Science Hill buildings, including the...